2024 年 5 月卷I · 第 75 题The project manager should use(75)tool for the purpose to report on the workremaining for projects.A.cumulative flow diagramB.burndown chartC.forecast estimationD.earnedvalue答案与解析需登录后查看登录|注册(免费)